Home builders ask this before anything else. A thumb rule gives you a planning figure for budgeting and for talking to suppliers. Your structural drawing gives the exact figure you should order against.
Thumb rules per square foot of built-up area
Built-up area means the area of every floor added together. A ground plus one house with 600 sq ft on each floor counts as 1,200 sq ft.
| Material | Per sq ft | For 1,200 sq ft |
|---|---|---|
| TMT steel | about 4 kg | about 4.8 tonnes |
| Cement | about 0.4 bag | about 480 bags |
| 20 mm aggregate | about 1.35 cft | about 1,620 cft |
| Sand or M-sand | about 1.2 cft | about 1,440 cft |
These are widely used rules for ordinary residential construction. Our material estimator uses the same figures, so you can try your own area and send the result to us on WhatsApp.
Why the real number differs
- Soil and foundation type. A raft foundation uses far more steel and concrete than isolated footings.
- Number of floors and column spans. Taller and wider-spanned buildings need heavier sections.
- The structural design. Your engineer chooses bar sizes and spacing for your loads.
- Steel grade. A higher grade can allow smaller bar sizes for the same strength.
- Cutting waste and lap lengths, which add to the length of bar you buy.
Use the figure to plan, then order against the drawing
Use the thumb rule to set a budget and to know roughly how many truckloads to expect. When your structural drawing is ready, order steel against the bar sizes and lengths it lists. Foundation steel comes first, column and beam steel next, and slab steel last, so you can take delivery in stages instead of storing everything on site.