Your structural drawing is the document your steel order should follow. Ordering from a thumb rule works for a budget. Ordering from the drawing avoids both shortages and surplus.
Seven things to read on the drawing
- Steel grade, for example Fe 500D or Fe 550D. See how the two compare.
- Bar diameters for each part: footings, columns, beams and slabs.
- Spacing and size of stirrups in columns and beams.
- Lap lengths, where one bar overlaps the next.
- Cover, the concrete thickness that protects the steel.
- Which members are the same size, so you can group them.
- Notes from the engineer on special bars or sections.
Ask for a bar bending schedule
A bar bending schedule, or BBS, lists each bar mark with its diameter, cut length and number of bars. It is the best basis for an order. Ask your engineer or contractor for one.
Turn the schedule into tonnes
For each diameter, add up the total length of bar in metres and multiply by the weight per metre. Weight per metre is the diameter in millimetres squared, divided by 162.
| Diameter | kg per metre |
|---|---|
| 8 mm | 0.395 |
| 10 mm | 0.617 |
| 12 mm | 0.889 |
| 16 mm | 1.580 |
| 20 mm | 2.469 |
Our weight calculator does this for any size. Add a small allowance for cutting waste and ask your engineer how much to add.
Order in stages
Order foundation steel first, then columns and beams, then slab steel. Staged delivery keeps steel clean and dry and reduces the risk of loss on site.